From the PHFD BC assigned to the fourth floor:
The crews did a fantastic job at the structure fire in Wheeling. The Fire Attack Lead-Out from the standpipe used all three 75-foot sections of 2-inch hose to reach the fire unit. As a reminder, Wheeling and Prospect Heights utilize the same 2″ Denver Load Packs. Excellent job by E39 applying water from the exterior with a 2 1/2″ prior to Wheeling E23 having their 2″ line in place. The exterior attack really helped E23 get their line deployed. E23 had a pressure of 140psi at the gauge.
I am also told there was significant spalling of the precast concrete ceiling/floor inside the fire unit.