Excerpts from the kenoshanews.com:

Work is continuing at the construction site of the new Kenosha Fire Department Fire Station No. 4, located at 4810 60th St. The new building, adjacent to the current station, will be twice the size at 29,344-square-feet and will include an additional 10,000-square foot tower for training purposes. The construction contract in the amount of $9.97 million was awarded to Stuckey Construction, of Waukegan, Ill. The completion of the project was slated for May 2022, but is ahead of schedule. According to Fire Chief Christopher Bigley, the Kenosha Fire Department “may get the keys in February.” If the building is finished by that time, operations will be fully run out of the new station in March.

Construction of a new fire station in Kenosha

Kenosha News photo

Construction of a new fire station in Kenosha

Kenosha News photo

click the link above for more photos

thanks Keith